Floor Voids

When you have a floor void that needs to be covered, we have the solution. Capable of covering long and wide spans, INTAKS’ strong aluminium planks join side-by-side and end-to-end, without lapping.

Installation process

Installation of floor void protection using INTAKS is straightforward:

  1. Place Interlocking Planks over floor void. Ensure the planks interlock side-to-side and end-to-end.
  2. Planks must overlap supporting surface a minimum of 200mm at each end.
  3. Timber battens (not supplied) 50mm high placed on all 4 sides of the planks and secured to concrete or timber floor with Tek screws to prevent movement of planks sideways and lengthways.
  4. Complete final checks and handover to site manager.
  5. Dismantle process is the reverse to installation.

Planks can also be installed on top of a supporting structure and secured in place where required.

Components

  • Interlocking Planks (part #ILP3 to #ILP6)

Scaffold / edge protection equipment & solutions